Work

The evidence belongs here.

Helmwize is a new company. We would rather show no case study than dress an example up as a customer result.

Illustrative only

What would a signed outcome look like?

These four cards are illustrative workflows — not client results. A case-study template activates only with a client-signed Stage 05.

CALL-EX-014Discharge port (illustrative)
Illustrative · synthetic records

Laytime exposure at discharge port

What changed
NOR tendered 06:40; SOF shows commencement of discharge 22:10. Charter party clause 14 allows 6 hours' turn time; 9 hours 30 minutes are counting against the charterer.
Evidence
SOF, page 2CP clause 14Agent's NOR email
Exposure
US$14,250 demurrage accruing at US$36,000/day
Confidence
High on times; medium on whether the shifting clause applies

Suggested step

Notify charterer of time counting; keep the SOF signed at each event.

Illustrative workflow, not a client result. This example changes nothing outside the page: no payment, no operational record, no message.

CALL-EX-208Terminal berth (illustrative)
Illustrative · synthetic records

Vessel call departed 3h 50m after the berth window

What changed
Cargo operations completed on time. Departure was held: pilot boarding logged 2h 10m after ready; outbound clearance documents completed 1h 40m after that.
Evidence
TOS event logPilot dispatch recordSingle-window clearance timestamps
Exposure
Berth occupancy lost: one call slot; next vessel waited 2h 30m at anchorage
Confidence
High on sequence; medium on cause of pilot delay

Suggested step

Review pilot allocation for the evening window; check clearance dependency on customs release.

Illustrative workflow, not a client result. This example changes nothing outside the page: no payment, no operational record, no message.

DOCK-EX-042Yard berth (illustrative)
Illustrative · synthetic records

Dry-dock scope variance against the original specification

What changed
Steel renewal item 42 quoted at 18 t from the specification; ultrasonic thickness report received on day 3 indicates 31 t. Two adjacent items carried the same pattern on the last three dockings for this vessel class.
Evidence
Specification item 42UT report, day 3Job history: dockings 2024-11, 2025-06, 2026-02
Exposure
Estimated 210 additional hours and 13 t steel; variation order not yet raised
Confidence
High on measurement; medium on owner acceptance

Suggested step

Raise the variation order today; re-plan the adjacent items before the blasting crew moves.

Illustrative workflow, not a client result. This example changes nothing outside the page: no payment, no operational record, no message.

CREW-EX-091Singapore, SG
Illustrative · synthetic records

Certificate expires before the next crew-change window

What changed
Chief Engineer's STCW endorsement expires 14 Oct. Vessel's next port with reliever availability is Singapore, 22 Oct. No reliever with the flag endorsement is currently free.
Evidence
Certificate scanCrew matrixVoyage scheduleReliever pool
Exposure
Vessel would sail non-compliant for 8 days; PSC detention risk
Confidence
High on dates; medium on reliever availability

Suggested step

Book the endorsement renewal in Colombo, 9 Oct; hold a reliever as fallback.

Illustrative workflow, not a client result. This example changes nothing outside the page: no payment, no operational record, no message.

Start

Start a Diagnostic

Start a Diagnostic